Atlas Corridor
Component

Abuja to Kaduna Standard Gauge Railway (SGR)

railway

Cities

Abuja
Nigeria
Kaduna
Nigeria

Distance

186km
new
186km
rehabilitated
– km
existing
– km

Cost

$0.9b
$874,000,000

Phases

operational, 2014

Objective

The cargo trains, carrying 800 tons of goods, will take one and a half hours to travel between the two cities

Description

The Abuja-Kaduna segment is the first to be implemented as part of the standard gauge project. The line features nine stations and a designed speed of 150km/h.

History

The railway replaces the Cape gauge Western Line built by the British in 1896–1927, which has a lower design capacity and is in a deteriorated condition

Finance

logo
$500000000 loan
Exim Bank of China Development bank
$374000000 investment
Nigerian Government Government

Contractors

logo
China Civil Engineering Construction Corporation Ltd
Construction company