Phases
Objective
Ensuring the projected 2025 volume of cargo transportation through the Saratov hub in the amount of 143.4 million tons. The project provides for the construction of a double-track electrified bypass Description
struction of the new Kurdyum– Ivanovsky electrified railway line (52.2 km) and electrified connect‑ ing tracks from the Tatishchevo and Burkin Stations. Construction of the second Lipovsky–Kurdyum electrified track (26.6 km). Construction and reconstruction of in‑ terchanges are envisaged at plac‑ es where rail tracks intersect with roads. The maximum travel speeds at the new sections will reach up to 90 km/h for freight trains and up to 120 km/h for p Finance
$760000000 investment
Federal Government of Russia
Government