Construction and modernisation of the Zahedan–Birjand railway section

railway

Cities

Zahedan
Iran (Islamic Republic of)
Birjand
Iran (Islamic Republic of)

Distance

446km
new
446km
rehabilitated
– km
existing
– km

Cost

$0.8b
$775,000,000

Phases

underConstruction,

Objective

A new straightening railway corridor which will join the lines con‑ necting Iran to Afghanistan and Turkmenistan. Upon completion of the new sections, the new port of Chabahar will receive railway approaches (today, only roads are being used), which will make it a fully fledged INSTC element

Description

The 460‑km Zahedan–Birjand section is an element of the future Chabahar–Zahedan–Mashhad main railway line (total length: 1,528 km) from the new port of Chabahar towards the major transport nodes of the country. Construction started in June 202

Finance

$ investment
Government of Islamic Republic of Iran Government

Operators

logo
Islamic Republic of Iran Railways
Company