Atlas Corridor
Component

Isiolo Airport

airport

Cities

Isiolo
Kenya

Cost

$235m
$235,000,000

Phases

operational, 2016

Objective

The airport is expected to boost the economy of Isiolo, Meru, Marsabit and Laikipia counties. Phase 1 was completed in 2013, and phase 2 was completed in 2016.

Description

Isiolo international airport is one of the three airport projects under the LAPSSET project. The airport was in existence before, however, it was upgraded to an international standard as part of the LAPSSET project.

History

In February 2013, Kenyan media reports indicated that the airport was undergoing renovations and improvements to International status. The improvements, at an estimated cost of US$11 million (KES:900 million), include lengthening the runway to 2,500 metres (8,200 ft).

Capacities

125000 Passengers Per year

Finance

logo
$ national government
Government Of Kenya Government
logo
$ african development bank
African Development Bank Development bank

Sources