Mae Sot-Myawaddy Border Crossing and Infrastructure Improvements

intraUrban

Cities

Mae Sot
Thailand

Distance

0km
new
– km
rehabilitated
– km
existing
– km

Cost

$130m
$130,000,000

Phases

operational, 2019

Objective

This new crossing will be dedicated to cross-border freight traffic and will avoid the congested urban areas. The bypass will link with a newly envisioned special trade zone on the Myanmar side.

Description

The project include a new bypass road and bridge to the north of the existing border crossing, currently located in the congested centers of the two border cities, Mae Sot and Myawaddy. The project consists of 16.745 km in Thailand and a 760-meter- long bridge across the Moei River at the border, and associated border-crossing facilities (BCF).

Finance

logo
$130000000
Government of Thailand Government