Karot Hydropower Project
power
Cities
Rawalpindi
Pakistan
Cost
$1.7b
$1,740,000,000
Phases
operational, 2022
Objective
Description
Karot Hydropower project is located on River Jhelum and was developed on a Build-Own-Operate-Transfer basis under CPEC.
Capacities
720 MW Electricity
Finance
$430670000 loan
China Development Bank Development bank
$430670000 investment
Exim Bank of China Development bank
$430670000 loan
Silk Road Fund Company
$100000000 loan
International Finance Corporation Bank
$316200000 investment
China Three Gorges Corporation Company
$23900000 investment
Yangtze Three Gorges Technology & Economy Development Co. Company
Operators
China Three Gorges Corporation
Company
Contractors
Yangtze Three Gorges Technology & Economy Development Co.
Company