Sirajganj Combined Cycle Power Plant Project (Units 2 & 3)
power
Cities
Sirajganj
Bangladesh
Cost
$0.5b
$510,000,000
Phases
operational, 2019
Objective
Description
Construction of Units 2 and 3 of the Sirajganj Combined Cycle Power Plant, comprising two 225 MW gas-fired combined cycle generating units together with associated generation and auxiliary facilities.
Capacities
450
mw
electricity
Finance
$200030000 loan
Exim Bank of China
Development bank
$59180000 loan
Bank of China
Bank
Operators
North-West Power Generation Co Ltd
Company
Contractors
China National Machinery Import Export Corporation