Rampura–Amulia–Demra (RAD) Expressway Project

intraUrban

Cities

Dhaka
Bangladesh

Distance

12.5km
new
12.5km
rehabilitated
– km
existing
– km

Cost

$261m
$261,000,000

Phases

underConstruction, 2028

Objective

Description

Construction of a 12.5 km four-lane access-controlled expressway, including an 8.15 km elevated section and a 4.35 km at-grade section, upgrading the existing Rampura–Amulia–Demra corridor between National Highways N1 and N2.

Finance

logo
$65000000 loan
Bank of China Bank
logo
$65000000 loan
Asian Infrastructure Investment Bank Development bank
logo
$50000000 loan
Development Bank of Singapore Bank

Contractors

logo
China Communications Construction Company, Ltd.
Company