Atlas Corridor
Component

Vung Ang 1 Coal-Fired Power Plant

power

Cities

Vung Ang
Viet Nam

Cost

$1.5b
$1,470,000,000

Phases

operational, 2015

Objective

Description

Construction of a 1,200 MW coal-fired power plant with two 600 MW units in the Vung Ang Economic Zone. PetroVietnam developed the plant, Vietnam Machinery Erection Corporation delivered the EPC works, and the project drew on a Chinese-led syndicated buyer's credit alongside Japanese and international bank financing.

Capacities

1200 MW Electricity

Finance

logo
$673000000 loan
China Development Bank Development bank
logo
$95000000 loan
Sumitomo Mitsui Banking Corporation Bank

Contractors

logo
Vietnam Machinery Erection Corporation
Company