Construction of a 400 MW hydropower plant on the Sesan River with eight generating units, a large reservoir and associated transmission and resettlement works. The project is one of Cambodia’s largest power plants and operates under a 45-year concession. Capacities
400
MW
Electricity
Finance
$175000000 loan
China Development Bank
Development bank
$175000000 loan
Exim Bank of China
Development bank
$175000000 loan
Bank of China
Bank
$175000000 loan
Shanghai Pudong Development Bank
Bank