Huadian Sihanoukville 700 MW Coal-Fired Power Plant
power
Cities
Sihanoukville
Cambodia
Cost
$1.3b
$1,283,000,000
Phases
operational, 2022
Objective
Description
Construction of a 700 MW supercritical coal-fired power plant comprising two 350 MW units, an 8,000-tonne coal berth and a 1.5 km 230 kV transmission connection. The plant was developed under a 35-year BOOT concession.