Dau Tieng Solar Power Plant

power

Cities

Dau Tieng Reservoir
Viet Nam

Cost

$225m
$225,000,000

Phases

operational, 2019

Objective

Description

Construction of a 240 MW ground-mounted solar photovoltaic plant and associated transmission facilities along the western edge of Dau Tieng Reservoir. The plant forms part of the wider 420 MW Dau Tieng 1–2 solar complex and was delivered by PowerChina subsidiaries using short-term deferred-payment finance before later refinancing.

Capacities

240 MW Electricity

Finance

logo
$128000000 loan
Industrial and Commercial Bank of China Bank

Contractors

logo
Sinohydro
Company
logo
Power Construction Corporation of China
Company