Moynak Hydropower Plant

power

Cities

Moinak
Kazakhstan

Cost

$346.6m
$346,600,000

Phases

operational, 2011

Objective

Description

This project is also known as the Mayinake Hydropower Project and the Construction of Moynak HPP on Charyn River Project. Moynak is also spelled 'Moinak'. It was planned in 2005 and completed in 2011.

Capacities

300 MW Electricity

Finance

logo
$200000000 loan
China Development Bank Development bank
$118600000 loan
Development Bank of Kazakhstan Bank
$28000000 investment
JSC Moinakskaya HPP Company

Contractors

logo
China International Water & Electric Corporation
Company
logo
China Geo-Engineering Corporation
Company
Chengdu Hydropower Investigation and Design Institute
Company