Mongolia : Regional Road Development and Maintenance Project: (Altanbulag - Darkhan - Ulaanbaatar Road)
road
Cities
Ulaanbaatar
✸ Mongolia
Darkhan
Mongolia
Altangulag
Mongolia
Distance
311km
new
– km
rehabilitated
311km
existing
– km
Cost
$277.6m
$277,600,000
Phases
underConstruction, 2026
Objective
"Efficiency and safety of Road transport within the project area and between countries improved" - CAREC website
Description
This is phase I & II of the regional road development and maintenance project. This phase, which began with approval in July 2018, specifically targets the rehabilitation of the Ulaanbaatar–Darkhan (193 km) and Darkhan–Altanbulag (118 km) sections.
Finance
$118500000 loan
Asian Development Bank
Bank
$1500000 grant
Asian Development Bank
Bank
$157000000 loan
European Bank for Reconstruction and Development
Development bank