Afghanistan : Transport Network Development Investment Program - Tranche 3

road

Cities

Dara-i-Suf
Afghanistan
Yakawlang
Afghanistan

Distance

178km
new
178km
rehabilitated
– km
existing
– km

Cost

$230m
$230,000,000

Phases

operational, 2021

Objective

"Better connectivity and efficiency through a fully complete North-South Corridor."-ADB

Description

Physical interventions under Tranche 3 include 178 km of reconstructed national road from Dar-i-Suf to Yakawlang linking the roads already completed under the ADB financed North South Corridor Project.

History

The project was scheduled to complete in 2017. The schedule was revised to be 2021. It is unclear whether the project is operational.

Finance

logo
$220000000 grant
Asian Development Bank Bank
logo
$10000000 investment
Government of Afghanistan Government